Provide a borehole

Build a borehole in Malawi through Urunji. Your support will enable us drill a borehole and provide portable water to families

Wondering what is the cost of drilling a borehole in Malawi? Well it depends on the depth, equipment used, materials, location and other factors. At Urunji we ensure that our partners and beneficiaries get value for money by following borehole drilling specifications and using the best borehole drilling companies in Malawi. 

URUNJI CHILD-CARE TRUST
CONSTRUCTION OF BOREHOLE 
 
Budget and Bill of quantities for Borehole ConstructionMALAWI KWACHA
Item No.DescriptionUnitQtyUnit PriceTotal Price
1. GENERAL 
1.1Mobilization and Demobilization of manpower,    
 equipment and construction materialsL.S1            1,500,000.00                        1,500,000.00
1.2Site preparation and rigging up before drilling                                            –  
 and site clearing  and rigging down after drillingL.S1            1,805,000.00                        1,805,000.00
1.3Geophysical Siting L.S1            1,030,000.00                        1,030,000.00
                                              –  
2. BOREHOLE DRILLING                                         –  
2.1Drilling the first 20m depthm20                 63,500.00                        1,270,000.00
2.2Drilling the from 20m downwardsm25                 59,500.00                        1,487,500.00
2.3Backfill Unsucessful BHsNo                                           –  
3. WELL LOGGING                                         –  
3.1Lithological LoggingLS1               263,500.00                           263,500.00
                                              –  
4. SUPPLY & INSTALLATION OF MATERIALS                                         –  
4.1Supply & installation of 110m outer diameter                                            –  
 UPVC casing including bail plug and centralisers                                            –  
 as specifiedm28                 15,000.00                           420,000.00
4.2Ditto but screen including centralisers as specified 12                 11,400.00                           136,800.00
5.0 GRAVEL PACKING AND WELL DEVELOPMENT                                         –  
5.1Supply and packing well sorted gravel as described                                            –  
 in the specificationm30.6            1,050,000.00                           630,000.00
5.2Supply and place puddle clay seal as described in the                                            –  
 specificationLS1               223,445.00                           223,445.00
5.3Well cleaning and development as described in the                                            –  
 specificationHr6               225,000.00                        1,350,000.00
6.1 PUMPING TEST                                         –  
6.1Constant test Hr6                 84,500.00                           507,000.00
6.2Recovery test Hr4                 38,000.00                           152,000.00
                                              –  
7. SANITARY & PROTECTION WORKS                                         –  
7.1Cement grouting up to 5m depth as described in the                                            –  
 specificationm30.1            1,050,000.00                           105,000.00
7.2Well head construction including 10m length                                            –  
 drainage ditch as per drawingLS1               585,000.00                           585,000.00
7.3Construction of Soak away including all associated                                            –  
 worksLS1               795,000.00                           795,000.00
7.4Cement pockets as per standardPK10                 21,500.00                           215,000.00
7.5Construction of cloth washing basin  completeLS1               350,000.00                           350,000.00
8. SUPPLY AND INSTALLATION OF HAND-PUMP                                         –  
8.1Supply & installation of Afridev pumps with stainless                                            –  
 steel pump rods, including spare parts tools andNo1            2,050,000.00                        2,050,000.00
 fishing equipment complete                                            –  
8.2Training of Water Point CommitteeLS1               435,000.00                           435,000.00
9. MISCELLANEOUS                                         –  
9.1Chemical and Bacteriological water quality testing                                             –  
 analysis and reportLS1               750,000.00                           750,000.00
9.2Well Disinfection LS1               645,000.00                           645,000.00
9.3Final borehole construction ReportNo1               195,000.00                           195,000.00
9.4NCIC levyNo1               180,000.00                           180,000.00
 TOTAL FOR ONE BOREHOLE                         17,080,245.00
      
10. HANDOVER CEREMONY 
10.1Printing of permanent signage on borehole 1               119,760.00                           119,760.00
10.2Printing of T-shirts for handover ceremony 10                 15,000.00                           150,000.00
      
11. MONITORING AND EVALUATION 
11.1Monitoring visits and reports to donor 11                              –                             150,000.00
      MALAWI KWACHA 
 Grand TOTAL  MWK                      17,500,005.00
 US DOLLAR     10,000.00

Frequently asked questions on borehole drilling in Malawi

Here are the frequently asked questions on borehole drilling in Malawi. Please note that these apply to Urunji. We are unable to provide information on behalf of other organisations or individuals
How much does it cost to drill a borehole in Malawi
At Urunji, it costs us USD 10,000 to drill a borehole to our required specifications.
How deep is a good borehole?
A good borehole should be at least 45 metres deep.
What is the average lifespan of a borehole?
On average, a borehole will last 20 to 30 years with proper preventative maintenance.
Can a borehole collapse?
We ensure that contractors install strong PVC pipes as they drill the boreholes. This prevents collapse.
Why do you use a manual pump?
The manual pump is cheaper to construct compared to the solar-powered systems. This is because we eliminate the cost of storage tank, stand construction, pump, solar panels and other equipment.
How long does it take to construct a borehole?
It takes us about 8 days from contract signing to commission a completed borehole.
How do I choose a borehole location?
The Urunji staff will suggest a borehole drilling location for you to support. We look at several factors before choosing a location. This includes yield, population of the area, absence of or ability to mitigate contamination and others.
How do you select borehole drilling contractors?
We reach out to approved borehole drilling companies in Malawi, source quotations from them, conduct an internal assessment and sign a contract with them. We only pay a deposit when they have brought equipment on site and complete the balance after successful handover.